October 15, 2026
Amul Dairy,Anand, inaugurated its new 66 kV Substation at the Dairy Plant, Anand, marking a significant milestone in strengthening power infrastructure to meet the dairy’s growing operational requirements and future expansion plans.
The substation was inaugurated by Shri Shabhesinh Parmar, Chairman, Amul Dairy in esteemed presence of Shri Vijaybhai Fulabhai Patel, Vice-Chairman, distinguished Board of Directors, Dr. Amit Vyas, MD, Amul Dairy, officials from Gujarat Energy Transmission Corporation Limited (GETCO Ltd.), MGVCL - Madhya Gujarat Vij Company Limited, and Amul dairy.
With the plant’s present maximum power demand of 4,800 kVA projected to rise to approximately 6,000 kVA, the new substation will enhance power reliability, improve operational efficiency and provide the necessary infrastructure to support ongoing and upcoming projects, including the proposed 60 TPD milk powder plant.
The substation features 5.8 km of high-capacity electrical cabling, advanced EHV circuit breakers, power transformers, SCADA-based monitoring and control, and integrated safety and surveillance systems - reinforcing the dairy’s commitment to reliable and efficient operations.
Impressions:
This strategic investment marks another step towards infrastructure modernisation and operational excellence, enabling Amul Dairy to support its expanding processing capabilities while continuing to serve its farmer-members and consumers with greater efficiency.
At Amul Dairy, Anand, we believe in strengthening infrastructure, powering progress, and empowering the cooperative movement.